ホーム > ブログ> Steel structure construction

Steel structure construction

July 06, 2022

1) Construction set-out


a. According to the design requirements and drawing requirements, and in accordance with the actual situation, the elevation and axis should be verified for accuracy.


b. Before construction, the theodolite should be used to match the axis, and the level should be used to determine the elevation. Also, make some records accordingly.


c. After determining the axis and elevation, put the large sample, and then put the small sample, the order cannot be reversed.


d. When positioning the rigid frame, try to avoid the collision between the rigid frame column foot and the bolt, so as not to deform or damage the bolt.


(2) Pre-embedded bolts in foundation concrete


a. Before the foundation concrete, check the size, length, elevation, and position of the bolts, and fix the embedded bolts.


b. After the foundation concrete is poured, it is necessary to clean up the residual concrete in time.


c. When pouring concrete, the positioning of the embedded bolts should be accurate to avoid changes in their displacement and elevation.


steel structure  01

お問い合わせ

Author:

Mr. Sean

Eメール:

sean.sun@jnhaiyao.com

Phone/WhatsApp:

+8615335317863

人気商品
You may also like
Related Categories

この仕入先にメール

タイトル:
イーメール:
メッセージ:

Your message must be betwwen 20-8000 characters

お問い合わせ

Author:

Mr. Sean

Eメール:

sean.sun@jnhaiyao.com

Phone/WhatsApp:

+8615335317863

人気商品

ホーム

Product

Phone

私たちに関しては

お問い合わせ

We will contact you immediately

Fill in more information so that we can get in touch with you faster

Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.

送信